Mtech CS 2014-2016 batch project schedule

Mtech CS 2014-2016 batch project schedule

Project topic finalization   Date : 11th September 2015
            Documents required : Project proposal (report and slides)

First review Date : 30th September 2015
            Expected level of completion : Literature survey + 5 % implementation
            Documents required : Report, presentation slides, previous review reports,  project diary.

Second review Date : 21st October 2015
            Expected level of completion : Literature survey + 10 % implementation
            Documents required : Report, presentation slides, previous review reports, Draft Survey                       paper, project diary.


Final Review Date : 9th November 2015
             Expected level of completion : Literature survey + 15 % implementation
             Documents required : Project final report, presentation slides, previous review reports,                         Survey paper, project diary.


Note : The project diary should be submitted to the project coordinator every monday after getting it signed from the respective guides.