Mtech CS 2015-2017 Batch Project Schedule
Project topic Presentation Date : 23rd September 2016
Expected level of completion : Literature survey
Documents required : Introduction, Problem statement, Survey of papers read. Project objective proposal (report and slides)
First review of Survey Date : 19th October 2016
Expected level of completion : Literature survey
Documents required : Report, presentation slides, previous review reports, project diary.
Second review of Survey and Design Presentation Date : 2nd & 3rd November 2016
Documents required : Introduction, Problem statement, Survey of papers read. Project objective proposal (report and slides)
Expected level of completion : Literature survey
Documents required : Report, presentation slides, previous review reports, project diary.
Second review of Survey and Design Presentation Date : 2nd & 3rd November 2016
Expected level of completion : Literature survey + Design (Architecture and working)
Documents required : Report, presentation slides, previous review reports, Draft Survey paper, project diary.
Design Presentation with complete set of algorithms and tool study Date: 22nd & 23rd November 2016
Expected level of completion : Literature survey + Design (Architecture and working, Algorithms,Sequence diagram etc)+Study of tools with 10 % implementation
Documents required : Report, presentation slides, previous review reports, Draft Survey paper, project diary.
Design Presentation with complete set of algorithms and tool study Date: 22nd & 23rd November 2016
Expected level of completion : Literature survey + Design (Architecture and working, Algorithms,Sequence diagram etc)+Study of tools with 10 % implementation
Documents required : Report, presentation slides, previous review reports, Draft Survey paper, project diary.
Final Review Date : 5th , 6th and 7th December , 2016
Expected level of completion : Literature survey + Design (Architecture and working, Algorithms,Sequence diagram etc)+Study of tools with 15 % implementation (Demo)
Documents required : Project final report, presentation slides, previous review reports, Survey paper, project diary.
Note 1 : The project diary should be submitted to the project coordinator every monday after getting it signed from the respective guides.
Note 2 : There is no change in the scheduled dates. If any one is not presenting thier work on scheduled date no further chances will be given. However students can request for scheduling the presentation on a date before the scheduled presentations.
No comments: